Câu 69: CPIM: Certified in Planning and Inventory Management
A plant is running at 87% capacity, and a scheduler is preparing to release open work orders to production. The best way to release orders without increasing work in process (WIP) is to:
Nội dung câu hỏi
A plant is running at 87% capacity, and a scheduler is preparing to release open work orders to production. The best way to release orders without increasing work in process (WIP) is to:
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. ensure all raw materials are available.
- B. ensure the bills of material (BOMs) are correct.
- C. release based on the availability of the bottleneck. — đáp án hiện tại
- D. release based on order due dates.