Câu 64: CPIM: Certified in Planning and Inventory Management

In an effort to maintain accurate due dates in the material requirements plan, a planner should primarily engage in which of the following activities?

Nội dung câu hỏi

In an effort to maintain accurate due dates in the material requirements plan, a planner should primarily engage in which of the following activities?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Convert planned orders to firm planned orders (FPOs) at the standard lead time indicated in the item master.
  2. B. Adjust due dates when the changes are substantial enough to impact material availability. — đáp án hiện tại
  3. C. Change expected due dates for purchased materials when a supplier shipment arrives early.
  4. D. Modify the master production schedule (MPS) when expected forecast becomes an actual customer order.