Câu 64: CPIM: Certified in Planning and Inventory Management
In an effort to maintain accurate due dates in the material requirements plan, a planner should primarily engage in which of the following activities?
Nội dung câu hỏi
In an effort to maintain accurate due dates in the material requirements plan, a planner should primarily engage in which of the following activities?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Convert planned orders to firm planned orders (FPOs) at the standard lead time indicated in the item master.
- B. Adjust due dates when the changes are substantial enough to impact material availability. — đáp án hiện tại
- C. Change expected due dates for purchased materials when a supplier shipment arrives early.
- D. Modify the master production schedule (MPS) when expected forecast becomes an actual customer order.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.