Câu 9: ACD301: Appian Certified Lead Developer
Towards the end of a sprint planning session, you discover that the business stakeholders have differing priorities on certain features, leading to confusion about what should be included in the upcoming sprint. How should you manage this situation to ensure the team can proceed effectively?
Nội dung câu hỏi
Towards the end of a sprint planning session, you discover that the business stakeholders have differing priorities on certain features, leading to confusion about what should be included in the upcoming sprint. How should you manage this situation to ensure the team can proceed effectively?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Engage the stakeholders in conversation to express their priority concerns and underlying timelines. Then, allow the product owner to decide on the priority. — đáp án hiện tại
- B. Prioritize the features that are technically easier to implement, allowing the team to make progress while waiting for the stakeholders to resolve their differences offline.
- C. Proceed with the sprint planning based on the original backlog to ensure the current sprint stays on schedule. Plan to resolve the prioritization conflict in the next sprint.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.