Câu 12: CCQM: Certified Construction Quality Manager
At the end of a construction project, a knowledge management review identifies that delays were consistently caused by late submittals from subcontractors. What is the most effective application of this knowledge for future projects?
Nội dung câu hỏi
At the end of a construction project, a knowledge management review identifies that delays were consistently caused by late submittals from subcontractors. What is the most effective application of this knowledge for future projects?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Note the issue in the final report and move on to close the project.
- B. Send a summary of the issue to the subcontractor involved for their records.
- C. Recommend a new milestone-based submittal tracking process. — đáp án hiện tại
- D. Require future teams to review the current project's punch list only.