Câu 37: CCQM: Certified Construction Quality Manager

During construction, a field team encounters a discrepancy between the structural drawing and the architectural layout. A Request for Information (RFI) is submitted, and the quality team is not included in the distribution, which of the following actions should be taken next?

Nội dung câu hỏi

During construction, a field team encounters a discrepancy between the structural drawing and the architectural layout. A Request for Information (RFI) is submitted, and the quality team is not included in the distribution, which of the following actions should be taken next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Wait until the RFI is resolved in the field and adjust inspection procedures afterward.
  2. B. Escalate the issue directly to the project owner for immediate resolution.
  3. C. Request inclusion in the RFI tracking process, review, and determine quality impacts. — đáp án hiện tại
  4. D. Assume the resolution has no quality implications unless otherwise informed.