Câu 23: CCQM: Certified Construction Quality Manager
During final quality closeout for a manufacturing facility, the quality manager reviews the turnover package and finds missing calibration certificates for pressure testing gauges used on safety-critical systems, which of the following actions should be taken next?
Nội dung câu hỏi
During final quality closeout for a manufacturing facility, the quality manager reviews the turnover package and finds missing calibration certificates for pressure testing gauges used on safety-critical systems, which of the following actions should be taken next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Accept the turnover package since the field test results meet performance criteria.
- B. Proceed with handover and note the missing certificates in the transmittal cover sheet.
- C. Reject the turnover package until all calibration certificates are received and validated. — đáp án hiện tại
- D. Allow the client to review and decide whether the certificates are necessary.