Câu 20: CCQM: Certified Construction Quality Manager

What is the most effective method for addressing deviations found during reviews, inspections, and testing across various project gates?

Nội dung câu hỏi

What is the most effective method for addressing deviations found during reviews, inspections, and testing across various project gates?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Make immediate on-the-spot corrections without further analysis to maintain project schedule and budget
  2. B. Postpone all corrective actions until the final project phase to avoid disrupting the current project schedule
  3. C. Focus corrections on deviations that are visible to external stakeholders
  4. D. Document the deviations, analyzing their root causes, and implementing effective corrective actions — đáp án hiện tại