Câu 28: CSQE: Certified Software Quality Engineer
A sprint started with 354 requirements. As the sprit progressed, 14 requirements were introduced, 6 requirements were removed, and 28 requirements were changed. What was the requirements volatility for this sprint?
Nội dung câu hỏi
A sprint started with 354 requirements. As the sprit progressed, 14 requirements were introduced, 6 requirements were removed, and 28 requirements were changed. What was the requirements volatility for this sprint?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 8.8%
- B. 11.9%
- C. 13.5% — đáp án hiện tại
- D. 15.7%