Câu 14: ISEB-SWT2: ISTQB-ISEB Certified Tester Foundation Level (BH0-010)
Which of the following activities should be performed during the selection and implementation of a testing tool? a) Determine whether the organization existing test process needs to change. b) Conduct a proof of concept. c) Implement the selected tool on a project behind schedule to save time. d) Identify coaching and…
Nội dung câu hỏi
Which of the following activities should be performed during the selection and implementation of a testing tool? a) Determine whether the organization existing test process needs to change. b) Conduct a proof of concept. c) Implement the selected tool on a project behind schedule to save time. d) Identify coaching and mentoring requirements for the use of the selected tool
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. a, b and c.
- B. b, c and d.
- C. a, c and d.
- D. a, b and d. — đáp án hiện tại