Câu 1: RCDD: Registered Communications Distribution Designer

An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping or manufacturing delay. Which action should the ICT distribution designer take?

Nội dung câu hỏi

An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping or manufacturing delay. Which action should the ICT distribution designer take?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Reject the submittal after verifying compliance with applicable standards.
  2. B. Approve the submittal after asking about additional compensating warranty offerings.
  3. C. Approve the submittal after verifying code compliance. — đáp án hiện tại
  4. D. Approve the submittal after verifying all significant features of the originally specified product are met.