Câu 5: PSA Sysadmin: PSA System Administrator
You are in the process of setting up your organization's Resources and learn that Resources in France will be working a 35-hour work week. What will you need to do to set them up with the proper work calendar?
Nội dung câu hỏi
You are in the process of setting up your organization's Resources and learn that Resources in France will be working a 35-hour work week. What will you need to do to set them up with the proper work calendar?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. As PSA only allows one work calendar, it is best to implement a 40-hour work calendar and then create a validation rule to only allow 35 hours a week.
- B. As the Work Calendar mostly impacts Utilization, set them up with a 40-work calendar, and then include the 35-hour hour work week in your utilization calculations.
- C. Create a separate 35-hour work calendar and associate it to the French Resources, including any specific French Holidays. — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.