Câu 35: 300-420: Designing Cisco Enterprise Networks (ENSLD)
A customer's current Layer 2 infrastructure is running Spanning Tree 802.1d, and all configuration changes are manually implemented on each switch. An architect must redesign the Layer 2 domain to achieve these goals:* reduce the impact of topology changes* reduce the time spent on network administration* reduce manua…
Nội dung câu hỏi
A customer's current Layer 2 infrastructure is running Spanning Tree 802.1d, and all configuration changes are manually implemented on each switch. An architect must redesign the Layer 2 domain to achieve these goals:* reduce the impact of topology changes* reduce the time spent on network administration* reduce manual configuration errorsWhich two solutions should the architect include in the new design? (Choose two.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Implement Rapid PVST+ instead of STP. — đáp án hiện tại
- B. Implement MST instead of STP.
- C. Use VTP to propagate VLAN information and to prune unused VLANs. — đáp án hiện tại
- D. Configure broadcast and multicast storm control on all switches.
- E. Configure dynamic trunking protocol to propagate VLAN information.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.