Câu 46: CMM: Certified Construction Manager

A new light rail project using P3 delivery receives a proposed change order from the concessionaire requesting a significant amount of money and a schedule extension. To validate it, the agency CM should FIRST

Nội dung câu hỏi

A new light rail project using P3 delivery receives a proposed change order from the concessionaire requesting a significant amount of money and a schedule extension. To validate it, the agency CM should FIRST

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. use the concessionaire’s Rough Order of Magnitude (ROM) estimate as the basis for entitlement.
  2. B. review the concessionaire’s stipulated price, schedule impact, and their justification for entitlement with supporting documentation. — đáp án hiện tại
  3. C. revise the concessionaire’s Estimate at Completion (EAC) based on this change.
  4. D. direct the concessionaire to stop work until this proposed change order is resolved and agreed to with the owner.