Câu 46: CMM: Certified Construction Manager
A new light rail project using P3 delivery receives a proposed change order from the concessionaire requesting a significant amount of money and a schedule extension. To validate it, the agency CM should FIRST
Nội dung câu hỏi
A new light rail project using P3 delivery receives a proposed change order from the concessionaire requesting a significant amount of money and a schedule extension. To validate it, the agency CM should FIRST
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. use the concessionaire’s Rough Order of Magnitude (ROM) estimate as the basis for entitlement.
- B. review the concessionaire’s stipulated price, schedule impact, and their justification for entitlement with supporting documentation. — đáp án hiện tại
- C. revise the concessionaire’s Estimate at Completion (EAC) based on this change.
- D. direct the concessionaire to stop work until this proposed change order is resolved and agreed to with the owner.