CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 21: CMM: Certified Construction Manager

The joint between a cast-in-place wall and a cast-in-place roof slab contains a waterstop for a sub-grade structure. While installing roof beams, the waterstop became dislodged from the already-placed wall. A non-conformance report was issued. The engineer of record’s repair detail showed to cut and remove the dislodg…

Nội dung câu hỏi

The joint between a cast-in-place wall and a cast-in-place roof slab contains a waterstop for a sub-grade structure. While installing roof beams, the waterstop became dislodged from the already-placed wall. A non-conformance report was issued. The engineer of record’s repair detail showed to cut and remove the dislodged waterstop sections. The authority/agency re- approved the detail as the waterstop is part of a secondary waterproofing system and the primary system was deemed sufficient. The contractor did not comply with the detail and placed the concrete roof slab over the dislodged material. In this scenario, which of the following options represents the BEST course of action?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. All slab concrete should be removed.
  2. B. The agency should accept as-is and rely on the primary system.
  3. C. Based on the engineer of record’s recommendation, the contractor should develop a repair detail and submit for approval. — đáp án hiện tại
  4. D. The concrete should be chopped out, rebar dowels should be drilled into the new slab, and the repair detail should be implemented.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề