Câu 33: CMM: Certified Construction Manager
A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month 10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned v…
Nội dung câu hỏi
A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month 10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million. Which statement most accurately portrays program status?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. On schedule, pay application accurately reflects percentage complete.
- B. Behind schedule, pay application accurately reflects percentage complete.
- C. On schedule, pay application exceeds percentage complete. — đáp án hiện tại
- D. Behind schedule, pay application exceeds percentage complete.