Câu 33: CMM: Certified Construction Manager

A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month 10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned v…

Nội dung câu hỏi

A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month 10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million. Which statement most accurately portrays program status?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. On schedule, pay application accurately reflects percentage complete.
  2. B. Behind schedule, pay application accurately reflects percentage complete.
  3. C. On schedule, pay application exceeds percentage complete. — đáp án hiện tại
  4. D. Behind schedule, pay application exceeds percentage complete.