Câu 30: CMM: Certified Construction Manager
A manufacturing company recently developed a new consumer product and the market has quickly outpaced the pilot production line. A new plant needs to be on line as soon as possible in order to prevent competition. In an attempt to accelerate the construction process, many verbal agreements were made for the purchase o…
Nội dung câu hỏi
A manufacturing company recently developed a new consumer product and the market has quickly outpaced the pilot production line. A new plant needs to be on line as soon as possible in order to prevent competition. In an attempt to accelerate the construction process, many verbal agreements were made for the purchase of equipment prior to formal written contracts. Later, as the plant began production, it became apparent that some of the equipment was not capable of achieving the intended quality or quantity. Which of the following MOST likely would have prevented this problem?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. A written equipment purchase contract complete with performance requirements — đáp án hiện tại
- B. A written equipment purchase contract complete with a scope of work
- C. A formal request for proposal focused on terms and conditions
- D. A contract with lease-purchase options