During the design phase of a project, the owner had requested the design team develop mitigating strategies due to expected budget concerns. During the procurement process, the agency CM should advise the owner consider

Nội dung câu hỏi

During the design phase of a project, the owner had requested the design team develop mitigating strategies due to expected budget concerns. During the procurement process, the agency CM should advise the owner consider

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. evaluating Schedule Alternates in the bid documents.
  2. B. incorporating Time and Material Alternates into the bid documents.
  3. C. evaluating Phase Alternates in the bid documents.
  4. D. incorporating Add/Deduct Alternates into the bid documents. — đáp án hiện tại