Câu 42: CMM: Certified Construction Manager

A CM is providing support on a $150 million construction project. The agency has a well-developed safety program; however, the contractor is planning to use an innovative, high-risk method for constructing the project. To minimize the owner’s risk, the CM should recommend that the owner

Nội dung câu hỏi

A CM is providing support on a $150 million construction project. The agency has a well-developed safety program; however, the contractor is planning to use an innovative, high-risk method for constructing the project. To minimize the owner’s risk, the CM should recommend that the owner

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. provide a safety coordinator to perform the necessary project safety functions on behalf of the contractor.
  2. B. ensure they have a contractor-controlled insurance program (CCIP) to cover the safety risk for the project.
  3. C. have the contractor submit a safety management plan for review and approval by the owner. — đáp án hiện tại
  4. D. modify the CM contract to include safety management to protect the owner’s interests.