Câu 22: PK0-004: CompTIA Project+
A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager's NEXT steps? (Choose two.)
Nội dung câu hỏi
A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager's NEXT steps? (Choose two.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays. — đáp án hiện tại
- B. The project manager should notify the project sponsor to update the schedule in the documentation because the project could potentially encounter delays.
- C. The project manager should adjust the schedule in the documentation and, if necessary, take steps to rush other areas of the schedule so the project will not encounter delays.
- D. The project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline. — đáp án hiện tại
- E. The project manager should update the procurement plan and action items to reflect the possible delay in the project timeline.