During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project. Which of the following actions should the project manager take?

Nội dung câu hỏi

During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project. Which of the following actions should the project manager take?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Alert the project sponsor of the situation. — đáp án hiện tại
  2. B. Contact the customer and request more funding.
  3. C. Announce the project will end early due to lack of funds.
  4. D. Attempt to save money in downstream activities.