CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 282: PK0-004: CompTIA Project+

A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?

Nội dung câu hỏi

A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Wait until the change requests are approved by the CCB. — đáp án hiện tại
  2. B. Approve the changes because the additional functionality is required to complete the process.
  3. C. Speak with the project sponsor and provide a detailed analysis of the changes and impacts to the project budget.
  4. D. Schedule the changes as part of the second phase of the project when additional funding will be available and work can be completed.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề