Câu 268: PK0-004: CompTIA Project+

A firm, fixed-price project is on pace to exceed the maximum defect rate identified in the project charter. The customer has stated the project must be delivered on time. Which of the following is the BEST option for the project to complete on time and within parameters?

Nội dung câu hỏi

A firm, fixed-price project is on pace to exceed the maximum defect rate identified in the project charter. The customer has stated the project must be delivered on time. Which of the following is the BEST option for the project to complete on time and within parameters?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Reduce the project scope. — đáp án hiện tại
  2. B. Crash the schedule.
  3. C. Request additional budget from the customer.
  4. D. Apply new resources to the project.