Câu 128: PK0-004: CompTIA Project+
A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked. Which of the following documents should the project team…
Nội dung câu hỏi
A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked. Which of the following documents should the project team reference to fast-track the project? (Choose two.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Scope management plan
- B. Configuration management plan
- C. Network diagram — đáp án hiện tại
- D. Project schedule — đáp án hiện tại
- E. Project plan