Câu 207: PK0-004: CompTIA Project+
A team member has finalized a discussion with the board of directors, but the Chief Financial Officer (CFO) is complaining about the large amount of money the project requires. Which of the following is the BEST change control process to follow?
Nội dung câu hỏi
A team member has finalized a discussion with the board of directors, but the Chief Financial Officer (CFO) is complaining about the large amount of money the project requires. Which of the following is the BEST change control process to follow?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Identify, implement, approve, evaluate, validate, update, communicate
- B. Identify, evaluate, approve, implement, validate, update, communicate — đáp án hiện tại
- C. Identify, approve, evaluate, implement, validate, update, communicate
- D. Identify, validate, evaluate, approve, implement, update, communicate