Câu 55: PK0-004: CompTIA Project+
Which of the following would indicate a project manager is working in a matrix-based organization?
Nội dung câu hỏi
Which of the following would indicate a project manager is working in a matrix-based organization?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The project manager has full authority over resources and the project.
- B. The project manager has no authority over the project resources and limited-to-no authority over the project.
- C. Resources align to the project, report to the project manager, and have no functional home at the end of the project.
- D. Resources report to business area functional managers and return to the functional area at the end of the project. — đáp án hiện tại