Câu 112: PK0-004: CompTIA Project+

A stakeholder with whom the project manager has worked on numerous occasions drops by and requests that the project management add two small items to the application under development. The stakeholder has seen the value of these changes in other applications and assures the project manager they are easy, quick changes…

Nội dung câu hỏi

A stakeholder with whom the project manager has worked on numerous occasions drops by and requests that the project management add two small items to the application under development. The stakeholder has seen the value of these changes in other applications and assures the project manager they are easy, quick changes. Which of the following BEST describes how the project manager should respond?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Take the request to the CCB — đáp án hiện tại
  2. B. Quickly make the changes
  3. C. Ask a project team member to make the changes
  4. D. Inform the sponsor of the stakeholder's request