A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects: ✑ Coordinate project schedule ✑ Manage to the triple constraint ✑ Provide performance feedback to team members' managersWhich of the following types of organizational structur…
Nội dung câu hỏi
A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects: ✑ Coordinate project schedule ✑ Manage to the triple constraint ✑ Provide performance feedback to team members' managersWhich of the following types of organizational structures did the new project manager MOST likely join?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Balanced matrix
- B. Strong matrix — đáp án hiện tại
- C. Functional
- D. Projectized