CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 100: PK0-004: CompTIA Project+

A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects: ✑ Coordinate project schedule ✑ Manage to the triple constraint ✑ Provide performance feedback to team members' managersWhich of the following types of organizational structur…

Nội dung câu hỏi

A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects: ✑ Coordinate project schedule ✑ Manage to the triple constraint ✑ Provide performance feedback to team members' managersWhich of the following types of organizational structures did the new project manager MOST likely join?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Balanced matrix
  2. B. Strong matrix — đáp án hiện tại
  3. C. Functional
  4. D. Projectized

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề