Câu 196: PK0-004: CompTIA Project+
If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?
Nội dung câu hỏi
If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
- B. The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report. — đáp án hiện tại
- C. The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.
- D. The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.
Cộng đồng