A change must be made to a project to comply with municipal code. The project manager updates the relevant shared project documents. The key stakeholders subsequently update the documents with new information. When the project deliverables are reinspected, they fail the inspection. Which of the following is theMOST li…

Nội dung câu hỏi

A change must be made to a project to comply with municipal code. The project manager updates the relevant shared project documents. The key stakeholders subsequently update the documents with new information. When the project deliverables are reinspected, they fail the inspection. Which of the following is theMOST likely reason for the failed inspection?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. There were insufficient resources assigned to the task.
  2. B. The prior document version was not reviewed.
  3. C. Version control processes were not applied. — đáp án hiện tại
  4. D. The CCB was not contacted.