Câu 146: PK0-004: CompTIA Project+
A new executive has joined the organization and is considering adding deliverables to the scope. The sponsor agrees with the executive but does not want to change the completion date. Which of the following options would be MOST useful to the project manager to accommodate the new scope without extending the completio…
Nội dung câu hỏi
A new executive has joined the organization and is considering adding deliverables to the scope. The sponsor agrees with the executive but does not want to change the completion date. Which of the following options would be MOST useful to the project manager to accommodate the new scope without extending the completion date? (Choose two.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Fast-track some tasks to free up time. — đáp án hiện tại
- B. Remove some of the previous deliverables.
- C. Document the impact to the scope.
- D. Request additional funds to get more resources. — đáp án hiện tại
- E. Deny the scope change.
- F. Perform regression analysis on the changes.