Câu 181: PK0-004: CompTIA Project+
A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?
Nội dung câu hỏi
A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Analyze the critical path and update the WBS with the new feature
- B. Add the new feature and reprioritize the product backlog
- C. Add the new feature to the next sprint and move the old feature to the following sprint — đáp án hiện tại
- D. Conduct a retrospective with the team to discuss the change and introduce the feature
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.