CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 2: PK0-004: CompTIA Project+

A project has activities on the critical path that must be completed before other activities can start. Task A is dependent on Task C before Task D can be completed. Task A requires task B to start. Task B takes twice as long to complete as Task C. Which of the following is the appropriate ordering of the critical pat…

Nội dung câu hỏi

A project has activities on the critical path that must be completed before other activities can start. Task A is dependent on Task C before Task D can be completed. Task A requires task B to start. Task B takes twice as long to complete as Task C. Which of the following is the appropriate ordering of the critical path?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. B, A, D
  2. B. C, B, D, A
  3. C. D, A, C
  4. D. B, C, A, D — đáp án hiện tại

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề