Câu 25: PK0-004: CompTIA Project+

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which of the following are critical for the project manager to provide?

Nội dung câu hỏi

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which of the following are critical for the project manager to provide?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Cost, schedule, organizational chart, and risks/issues
  2. B. Risks/issues, cost, RACI chart, and action items
  3. C. Schedule, cost, risks/issues, and milestones — đáp án hiện tại
  4. D. Action items, organizational chart, schedule, and NDA