Câu 124: PK0-004: CompTIA Project+
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
Nội dung câu hỏi
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Revise the project plan. — đáp án hiện tại
- B. Update the issue log.
- C. Request additional funding.
- D. Issue a change request.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.