Câu 266: PK0-004: CompTIA Project+
A project manager is performing resource leveling and notices one of the functional testers is assigned 40% in a second project. The project manager needs the resource to be 100% dedicated to the project; otherwise, the testing phase jeopardizes the delivery date. Which of the following should the project manager doNE…
Nội dung câu hỏi
A project manager is performing resource leveling and notices one of the functional testers is assigned 40% in a second project. The project manager needs the resource to be 100% dedicated to the project; otherwise, the testing phase jeopardizes the delivery date. Which of the following should the project manager doNEXT?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Ask the resource manager to deallocate the resource from the second project.
- B. Ask the resource manager to assign a new resource with 40% of allocation.
- C. Keep the resource 100% allocated in the project, as per the initial plan.
- D. Change the resource to 60% of allocation and review the mitigation plan. — đáp án hiện tại