Câu 266: PK0-004: CompTIA Project+

A project manager is performing resource leveling and notices one of the functional testers is assigned 40% in a second project. The project manager needs the resource to be 100% dedicated to the project; otherwise, the testing phase jeopardizes the delivery date. Which of the following should the project manager doNE…

Nội dung câu hỏi

A project manager is performing resource leveling and notices one of the functional testers is assigned 40% in a second project. The project manager needs the resource to be 100% dedicated to the project; otherwise, the testing phase jeopardizes the delivery date. Which of the following should the project manager doNEXT?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask the resource manager to deallocate the resource from the second project.
  2. B. Ask the resource manager to assign a new resource with 40% of allocation.
  3. C. Keep the resource 100% allocated in the project, as per the initial plan.
  4. D. Change the resource to 60% of allocation and review the mitigation plan. — đáp án hiện tại