Câu 162: PK0-005: CompTIA Project+
A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do NEXT to comply with the new legislation?
Nội dung câu hỏi
A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do NEXT to comply with the new legislation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Use only full-time employees even if the project is delayed. — đáp án hiện tại
- B. Hire all team members to avoid any delay in the project.
- C. Close the contract and pay the contractors cash for the remainder of the project.
- D. Look for an overseas vendor to finalize the project work.