A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
Nội dung câu hỏi
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Time and materials contract — đáp án hiện tại
- B. Master service agreement
- C. Fixed-price contract
- D. Statement of work
- E. Cost-plus agreement