A project plan included budgeted funding to set up only a specified number of workstations. A department manager asked a project manager to set up additional workstations just in case the workstations are needed in the future. Which of the following should the project manager do?

Nội dung câu hỏi

A project plan included budgeted funding to set up only a specified number of workstations. A department manager asked a project manager to set up additional workstations just in case the workstations are needed in the future. Which of the following should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask the sponsor for additional funding to accommodate the request.
  2. B. Escalate the request to the senior management team.
  3. C. Advise that a change request would need to be approved. — đáp án hiện tại
  4. D. Instruct the project team to set up the additional workstations.