Câu 153: PK0-005: CompTIA Project+

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the BEST tool to track this data?

Nội dung câu hỏi

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the BEST tool to track this data?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Gantt chart
  2. B. Project organization chart
  3. C. Program Evaluation Review Technique chart
  4. D. Milestone chart — đáp án hiện tại