Câu 35: PK0-005: CompTIA Project+
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
Nội dung câu hỏi
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Validate against the scope statement and ask for sign-off. — đáp án hiện tại
- B. Run a control chart to ensure the quality of the deliverables.
- C. Review the risk register and close up residual risks.
- D. Start the training and handoff for the operations team.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.