CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 48: PK0-005: CompTIA Project+

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Nội dung câu hỏi

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Work with the project scheduler to update the project timeline. — đáp án hiện tại
  2. B. Communicate to the stakeholders about the updated timeline.
  3. C. Ask the development team to fast-track upcoming activities.
  4. D. Add two resources so the critical activities will finish on time.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề