Câu 167: PK0-005: CompTIA Project+
A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:• Two developers• High uncertainty about existing systems• Risk of frequent requirement changes• Tight deadlinesWhich of the following project methodologies would be BEST to use in this situation?
Nội dung câu hỏi
A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:• Two developers• High uncertainty about existing systems• Risk of frequent requirement changes• Tight deadlinesWhich of the following project methodologies would be BEST to use in this situation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. PRINCE2
- B. Scrum
- C. SAFe
- D. XP — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.