Câu 173: PK0-005: CompTIA Project+
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the p…
Nội dung câu hỏi
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do FIRST?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Escalate the change to the CCB.
- B. Review the requested change. — đáp án hiện tại
- C. Document the change recommendations.
- D. Validate the implementation of the requested change.