Câu 108: PK0-005: CompTIA Project+

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take NEXT?

Nội dung câu hỏi

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take NEXT?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Assign more resources to complete similar stories in the future.
  2. B. Break the stories into workable items that can be completed within one sprint. — đáp án hiện tại
  3. C. Extend the sprint duration when required with the approval of the product owner.
  4. D. Release the current progress into production and carry over the rest of the code for the next sprint.