Câu 112: PK0-005: CompTIA Project+

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

Nội dung câu hỏi

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Decline because it is not included in the project scope.
  2. B. Assess the impact of the request and create a change request. — đáp án hiện tại
  3. C. Create new functional and non-functional requirements for mobile devices.
  4. D. Revise the baseline of the project plan by adding the new requirements.