Câu 128: PK0-005: CompTIA Project+

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the bu…

Nội dung câu hỏi

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Escalate the finding to the change control board.
  2. B. Add a risk to the risk register for validation.
  3. C. Consult the RACI matrix to identify ownership of the risk.
  4. D. Have a meeting with the project sponsor and main stakeholders. — đáp án hiện tại