A managed services team is planning a four-node VxRail cluster to support a new customer with limited resources in the data center. Which statement describes the physical switch considerations that can support the design?

Nội dung câu hỏi

A managed services team is planning a four-node VxRail cluster to support a new customer with limited resources in the data center. Which statement describes the physical switch considerations that can support the design?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. An OOB Management switch is required to support iDRAC management within the configuration.
  2. B. VxRail network traffic uplinks and iDRAC management uplinks can be combined on the same TOR switches. — đáp án hiện tại
  3. C. IPv6 Multicast technology must be supported by the TOR switches for manual node discovery.
  4. D. A VDS must be preconfigured with an LACP dynamic LAG to support resource-intense VSAN traffic.