Câu 3: DNDNS-200: Dell Networking Professional Exam
Refer to the Exhibit. A network engineer receives the output shown when removing MLAG from a pair of N-Series switches. Which sequence of steps must the engineer complete to remove the vpc peer-link from Port Channel 1?
Nội dung câu hỏi
Refer to the Exhibit. A network engineer receives the output shown when removing MLAG from a pair of N-Series switches. Which sequence of steps must the engineer complete to remove the vpc peer-link from Port Channel 1?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Shut down the Port Channel interface Issue the no vpc peer-link command on the Port Channel
- B. Remove the vpc feature using the no feature vpc command Issue the no vpc peer-link command on the Port Channel
- C. Remove the channel-group command from all members of the Port Channel Issue the no vpc peer-link command on the Port Channel
- D. Remove peer-keepalive enable using the no peer-keepalive enable command — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.