Câu 11: DSDPS-200: Dell PS Series Storage Profrssional Exam
A customer is moving to a new datacenter and needs to put the existing two members into a new subnet. Each array has two iSCSI ports. The group does NOT use a dedicated management port. What is the correct sequence of steps to change all physical and group IPs on the members to the new subnet?
Nội dung câu hỏi
A customer is moving to a new datacenter and needs to put the existing two members into a new subnet. Each array has two iSCSI ports. The group does NOT use a dedicated management port. What is the correct sequence of steps to change all physical and group IPs on the members to the new subnet?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. - Change 1st port array physical ports first - Change Group IP second - Change 2nd port array physical ports last
- B. - Change Group IP first - Change 2nd port array physical ports second - Change 1st port array physical ports last
- C. - Change 1st port array physical ports first - Change 2nd port array physical ports second - Change Group IP last — đáp án hiện tại
- D. - Change 2nd port array physical ports first - Change Group IP second
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.