Câu 34: E20-542: VMAX3 Solutions and Design Specialist Exam for Technology Architects

After an SRDF failover operation, production work has been moved to the remote site. A large number of invalid tracks have accumulated that need to be synchronized back to the R1 volumes. Which SRDF operation can reduce the re-synchronization time, while continuing production work on the remote site?

Nội dung câu hỏi

After an SRDF failover operation, production work has been moved to the remote site. A large number of invalid tracks have accumulated that need to be synchronized back to the R1 volumes. Which SRDF operation can reduce the re-synchronization time, while continuing production work on the remote site?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Update — đáp án hiện tại
  2. B. Failback
  3. C. Restore
  4. D. Establish